Kitchen and bathroom renovations: what to tell your electrician before demo day.
by David Millar · Licensed electrician REC-22849The three-visit sparky problem is real, and it almost always starts with an electrical scope that was never properly agreed before demolition. Here's how to avoid it.

Kitchen and bathroom renovations are where electrical problems compound fastest. The walls are open for a short window during construction; miss it and any change to the electrical layout (a relocated oven, an extra power point, a heated towel rail that needs its own circuit) means cutting into finished plasterboard, patching, repainting, and bringing the sparky back for another day rate. This guide covers the scope decisions to lock in before demolition, the AS/NZS 3000 requirements for wet areas, and how the electrical work sequences with the builder.
Why the scope needs to be locked in before demo day
When a kitchen or bathroom goes to bare framing, an electrician can run cables through open stud bays and top plates with minimal disruption. Once the insulation goes in and the plasterboard is fixed, every cable route becomes a chase or a surface conduit. That costs time, looks worse, and usually costs more than doing it right in the rough-in.
The decisions that need to be made before the walls come down:
- Where is the oven going, and does its circuit need to move with it?
- Is a dishwasher being added? That needs a dedicated circuit if one doesn’t already exist.
- Is the rangehood position changing? New duct route, possibly a new GPO for a recirculating model.
- Are GPO positions changing? A splash zone that was once acceptable may now be in the wrong position relative to the new sink or bench layout.
- Is a heated towel rail going in? Hardwired or plug-in? Hardwired needs a circuit and a switched connection unit.
- Is an exhaust fan being added or relocated? Which circuit does it go on, and does it need humidity sensing?
None of these are hard to accommodate in rough-in. All of them are expensive to fix after fit-off.
What AS/NZS 3000 requires in wet areas
The Wiring Rules have specific provisions for kitchens and bathrooms that go beyond what applies to the rest of the house.
Bathroom zones
AS/NZS 3000 defines zones within bathrooms based on distance from water sources. Zone 0 is inside the bath or shower. Zone 1 is the space directly above and around it, and Zone 2 extends beyond that; the standard sets the exact dimensions, and the restrictions on equipment tighten as you get closer to the water. In practical terms: general-purpose power points cannot be installed in Zone 1 or Zone 2, shaver sockets have specific requirements, and luminaires must have appropriate IP ratings for their zone.
In practice this means that if a bathroom renovation moves the shower position, or adds a freestanding bath, the zone boundaries shift, and GPOs or light fittings that were previously compliant may no longer be. We check this as part of the scope, not after the tiler has finished.
RCD protection in wet areas
AS/NZS 3000 requires RCD protection on final sub-circuits in domestic installations, including the bathrooms and kitchens. If the existing switchboard has RCDs covering these circuits, that requirement is met. If the board is an older type without RCDs, or if RCDs are present but circuits have been added or modified, we verify coverage as part of the renovation scope.
In a full renovation where circuits are being moved or replaced, it is practical to ensure the switchboard is fully compliant at the same time. Doing a half-job (replacing kitchen circuits but leaving a non-RCD-protected lighting circuit in place) creates a compliance grey area.
Kitchen GPOs and arc fault consideration
A full kitchen renovation is one of the few residential contexts where arc fault detection is worth raising. AS/NZS 3000:2018 does not currently mandate arc fault circuit interrupters (AFCIs) in Australian residential installations the way US code does. But in a full kitchen reno where you are running new circuits behind new cabinetry, it is worth discussing.
The practical reason: kitchen GPOs behind built-in appliances (the fridge, the dishwasher, the rangehood) are difficult to access and prone to years of vibration and heat stress. An AFCI detects the electrical signature of a loose or damaged connection before it causes a fire. The extra cost at installation time is small relative to the cost of accessing those connections later.
This is not a compliance requirement. It is a sensible option to consider when the circuits are already being replaced anyway.
The oven circuit: move it properly or leave it where it is
Ovens are heavy-current loads. A 32 A circuit at 230 V delivers about 7.4 kW, so a large full-size oven drawing around 9 kW needs its own 40 A circuit with appropriately sized cable. When a kitchen renovation moves the oven position, that circuit needs to move too. You cannot run a 10 A extension lead from an existing socket and call it done.
The oven circuit is usually run in 6 mm² or 10 mm² cable depending on the load and run length. Moving it means chasing cable through a wall or ceiling cavity, adding a new connection unit or cooktop isolator at the new position, and updating the circuit documentation on the switchboard. This is a rough-in task. If it is not in the scope before demolition, it will be a costly late addition.
The same applies to induction cooktops if the renovation is swapping from gas to electric. A typical induction cooktop draws 7.2–14 kW. A double oven plus induction cooktop combination on a single household circuit is not acceptable. These loads need separate circuits, properly sized.
Sequencing with the builder
The right electrical sequence in a renovation looks like this:
- Scope agreed with electrician before demolition: circuit list, fixture locations, new positions confirmed
- Electrician attends for rough-in after demolition and framing, before insulation and plasterboard
- Builder continues: insulation, plasterboard, plastering, painting, tiling
- Electrician returns for fit-off after painting and tiling are complete (installing GPOs, switches, light fittings, connecting appliances)
- If new circuits are added, a Certificate of Electrical Safety is issued: this is the compliance documentation the homeowner keeps
Where things go wrong is when step 1 is skipped. The builder starts, the electrician is called partway through, the scope is agreed hastily, and there are always things that were not anticipated because no one walked through the plan systematically beforehand.
The “come back three times” problem
The scenario most homeowners have experienced:
- Visit 1: rough-in (cables run, first fix done)
- Visit 2 (unplanned): homeowner decides mid-construction to add a second GPO under the bench, or the range position changed by 300 mm and the circuit connection is now in the wrong spot
- Visit 3: fit-off
Each additional visit is a minimum call-out cost plus travel. More importantly, visit 2 often happens after the plasterboard is up, which means cutting and patching. A disciplined pre-renovation conversation, even 30 minutes with the plans on the table, eliminates most of this.
What to bring to that conversation
When you brief your electrician before a kitchen or bathroom reno, bring:
- The builder’s floor plan, even if hand-drawn, showing the new layout
- Appliance specs for anything new: oven model, induction cooktop model, rangehood (recirculating or ducted), dishwasher
- Proposed positions for heated towel rails, exhaust fans, any heated floor (in-slab heating has its own wiring requirements)
- The existing switchboard age and any known limitations
If you are not sure about the switchboard age or its RCD coverage, we can check that before the reno starts and give you an accurate scope rather than a discovery on the day.
Renovation electrical work is straightforward when it is planned. It becomes expensive when it is reactive. Talk to us about your renovation before demolition starts and we’ll scope the electrical side properly from the beginning.